Written from direct SSH inspection of both real clusters (node1-3 prod HA, dev-k8s-1-3 dev) done while building the GitLab CI + ArgoCD pipeline (MR !1) - not re-derived from the aspirational docs/manifests that predated that inspection. ARCHITECTURE.md: system diagram (clients, both clusters, Stalwart, EJBCA CA, the CI+ArgoCD flow) plus the storage-coupling fact that everything else hinges on - 4 RWO PVCs + strategy:Recreate is why the app is single-replica today. SANDBOX-DEV-MANUAL.md: day-to-day branch/MR/CI/ArgoCD flow, one-time bootstrap, troubleshooting, and what's explicitly out of scope for normal dev work (the CA, the still-inert prod overlay). PRODUCTION-SCALE-OUT-PLAN.md: phased path to a 100k+-user production deployment on node1-3 - breaking the storage coupling first (rook-ceph CephFS RWX as the fast path, migrating mutable state into the already-installed-but-unused CNPG Postgres as the correct one), then autoscaling, Stalwart's own scaling track, networking/edge, the observability gap (none found on either cluster), security hardening, load testing, DR, and the go-live sequence. Includes a "scale at any time" manual lever, not just HPA.
169 lines
9.0 KiB
Markdown
169 lines
9.0 KiB
Markdown
# VNCmail+ — Production Scale-Out Plan (target: 100k+ users, scalable on demand)
|
||
|
||
Goal: take VNCmail+ from "doesn't exist on `node1-3`" to a production
|
||
deployment that can grow past 100k users and be scaled **at any time** —
|
||
both automatically (load-driven) and on a single manual command (ahead of an
|
||
expected spike), not just reactively.
|
||
|
||
Read [ARCHITECTURE.md](ARCHITECTURE.md) first, especially "The storage
|
||
coupling" section — it's the reason this is phased the way it is.
|
||
|
||
## Where things stand today (verified by direct inspection, not assumed)
|
||
|
||
- `node1-3` is a healthy 3-node HA microk8s cluster (rook-ceph, traefik,
|
||
metallb, cert-manager) with **zero application workloads and zero
|
||
ClusterIssuers**. It's a clean slate, not a half-finished deployment.
|
||
- `rook-ceph` is already there, with both `ceph-rbd` (RWO) and **`ceph-cephfs`
|
||
(RWX, distributed)** StorageClasses available — the key piece that makes
|
||
multi-replica VNCmail+ possible without inventing new infrastructure.
|
||
- `cnpg-system` (CloudNativePG, a Postgres operator) is **already installed
|
||
on both clusters** and currently unused by anything. This is the natural
|
||
home for the app's mutable state once it moves off local files (Phase 1).
|
||
- No Prometheus/Grafana/logging stack was found on either cluster — this is
|
||
a real gap, not a "probably fine," and it's a prerequisite for safe
|
||
autoscaling (HPA needs a metrics pipeline) and for running anything at
|
||
100k-user scale with any visibility into it.
|
||
- Stalwart's own scaling story is **not covered here** — it's a separate
|
||
system owned by the backend/infra side of this decision. It's called out
|
||
explicitly at each phase below because VNCmail+ scaling is moot if
|
||
Stalwart can't handle the same load; plan the two together, not
|
||
sequentially.
|
||
|
||
## Phase 1 — Break the storage coupling (blocking; do this first)
|
||
|
||
Today: 4 RWO PVCs, `strategy: Recreate`, one pod max, ever. Two ways to fix,
|
||
pick based on how much time you have before you need >1 replica:
|
||
|
||
**Tactical (fast, days)**: switch the 4 PVCs to the `ceph-cephfs` StorageClass
|
||
(RWX) and the Deployment `strategy` to `RollingUpdate`. This alone unblocks
|
||
multiple replicas with no code changes. Real risk: `admin-state`/`telemetry`
|
||
are multi-writer files on a shared filesystem — fine at low write volume
|
||
(login timestamps, audit log, version-check state), but it's a shortcut, not
|
||
the target architecture. `settings` (per-user, keyed by `hash(username:serverUrl)`)
|
||
has no cross-writer conflict risk since each user only ever writes their own
|
||
file — this one is safe on RWX indefinitely.
|
||
|
||
**Structural (correct, weeks)**: migrate `admin-state` and `telemetry` into
|
||
CNPG Postgres (already installed, unused) — proper multi-writer semantics,
|
||
no filesystem-locking edge cases, and it's the natural place for this kind
|
||
of low-volume operational state anyway. Keep `admin` (config) as a
|
||
**read-only mount** after setup — `ADMIN_CONFIG_READONLY=true` is already a
|
||
supported mode (`lib/admin/paths.ts`), so this can be baked into the image
|
||
or a ConfigMap at deploy time instead of a writable volume at all. `settings`
|
||
can either stay on CephFS RWX (it's genuinely safe there) or also move to
|
||
Postgres if you want zero PVCs in the final state.
|
||
|
||
Either way: this is the one item that has to happen before Phase 2 means
|
||
anything. Everything downstream assumes replicas > 1 is possible.
|
||
|
||
## Phase 2 — Autoscaling & headroom
|
||
|
||
- Install a metrics pipeline (`metrics-server` at minimum for HPA;
|
||
Prometheus+Grafana for real visibility — see Phase 5, do it once, not twice).
|
||
- `HorizontalPodAutoscaler` on CPU/memory to start; revisit with a custom
|
||
metric (JMAP request rate, active WebSocket/SSE connections) once you have
|
||
real traffic shape.
|
||
- `PodDisruptionBudget` so rolling updates and node maintenance don't drop
|
||
below your minimum replica count.
|
||
- Re-size `resources.requests/limits` from real load-test numbers (Phase 7)
|
||
— the sandbox's `100m/256Mi` requests are sandbox-appropriate, not
|
||
production-appropriate; don't carry them forward by default.
|
||
- **The "scale at any time" requirement**: HPA covers load-driven scaling,
|
||
but also document (and rehearse once) a single manual command to add
|
||
capacity ahead of a known event, before HPA would react:
|
||
`kubectl -n vncmail-prod scale deploy/vncmail-plus --replicas=N` or
|
||
bumping the HPA's `minReplicas`. This should be a one-line runbook entry,
|
||
not something someone has to figure out under pressure.
|
||
|
||
## Phase 3 — Stalwart scaling (parallel track, not this repo's code)
|
||
|
||
VNCmail+ has no database and does no caching of its own — every request is
|
||
a live JMAP call to Stalwart. At 100k users, Stalwart's own architecture
|
||
decision matters as much as anything in this repo:
|
||
|
||
- Storage backend: Stalwart supports RocksDB (single-node) or FoundationDB
|
||
(distributed, HA) — FoundationDB is the one that scales past a single
|
||
node.
|
||
- Blob storage: point Stalwart's message-blob storage at an S3-compatible
|
||
backend — rook-ceph's object gateway (RGW), if enabled, is already
|
||
sitting on the same cluster.
|
||
- Confirm Stalwart's own capacity plan (connections, IOPS, memory) against
|
||
the same 100k-user target this doc is aiming for, ideally before Phase 7's
|
||
load test, not after it fails.
|
||
|
||
## Phase 4 — Networking & edge
|
||
|
||
- Create a real `ClusterIssuer` on `node1-3` — **none exists today**. Decide
|
||
ACME account + DNS-01 or HTTP-01 solver before anything else in this phase.
|
||
- Decide the real production hostname (still an open decision — see
|
||
`deploy/k8s/overlays/prod/patch-ingress.yaml`'s placeholder).
|
||
- Rate limiting at the Traefik ingress (a `Middleware` CRD) before opening
|
||
up publicly at this scale — nothing enforces this today.
|
||
- Consider a CDN in front of `_next/static` and other cacheable assets to
|
||
keep origin load down as user count grows.
|
||
|
||
## Phase 5 — Observability
|
||
|
||
Stand up Prometheus + Grafana (or point at existing org tooling if one
|
||
already covers this cluster — worth checking before installing a second
|
||
stack) **before** Phase 2's HPA and **before** Phase 7's load test — you
|
||
need to see what's happening in both. At minimum: request rate/latency/error
|
||
rate per pod, JMAP call latency to Stalwart, PVC/CephFS I/O if Phase 1 went
|
||
the tactical route, and alerting on pod restarts / ImagePullBackOff / cert
|
||
expiry.
|
||
|
||
## Phase 6 — Security hardening
|
||
|
||
- `NetworkPolicy` for `vncmail-prod`, mirroring the `vnc-ca` namespace's
|
||
existing default-deny-plus-narrow-allow pattern — nothing enforces
|
||
network isolation for `vncmail-prod` today.
|
||
- Confirm the microk8s CNI on `node1-3` actually enforces `NetworkPolicy`
|
||
(Calico does, flannel-without-a-policy-plugin silently doesn't — the
|
||
`vnc-ca` README already flags this exact trap, re-verify for this
|
||
namespace too rather than assuming).
|
||
- Image scanning in the CI build stage.
|
||
- S/MIME CA promotion to prod is its own separate, human-only runbook
|
||
(`deploy/k8s/ca/README.md` §9) — sequence it, don't bundle it into this
|
||
plan's steps.
|
||
|
||
## Phase 7 — Load testing & capacity planning
|
||
|
||
Model the actual target before guessing replica counts: concurrent users,
|
||
JMAP poll/push connection count, expected sync volume per user, attachment
|
||
upload size/frequency. Run a load test against a **prod-shaped** deployment
|
||
(real storage backend from Phase 1, real Stalwart capacity from Phase 3, HPA
|
||
from Phase 2) before the real cutover — a load test against the sandbox's
|
||
single-hostPath-replica setup would tell you nothing useful about 100k users.
|
||
|
||
Recommend a staged ramp for the actual rollout (soft-launch a cohort →
|
||
watch Phase 5's dashboards → widen) rather than a single cutover to the full
|
||
100k target on day one.
|
||
|
||
## Phase 8 — Backup & DR
|
||
|
||
- rook-ceph snapshot policy for whatever PVCs remain after Phase 1.
|
||
- Stalwart's own backup strategy (backend-owned, but confirm it exists and
|
||
is tested — a mail server's data loss is a much worse incident than this
|
||
app's).
|
||
- A written, rehearsed restore runbook — not just "backups exist."
|
||
|
||
## Go-live sequence (once Phases 1–6 are actually done, not just planned)
|
||
|
||
1. Register `node1-3` as an ArgoCD-managed cluster (`argocd cluster add`, or
|
||
an equivalent ServiceAccount+kubeconfig secret) — not done yet, and
|
||
deliberately not done before this point.
|
||
2. Fill in the real values in `deploy/k8s/overlays/prod/` (hostname, prod
|
||
Stalwart's `JMAP_SERVER_URL`) and apply `deploy/argocd/vncmail-prod-app.yaml`.
|
||
3. Create the real `vncmail-env` secret + registry pull secret in
|
||
`vncmail-prod`, by hand, same as dev's one-time bootstrap.
|
||
4. Merge `dev` → `main` (fast-forward only — `git log dev..main` must be
|
||
empty first).
|
||
5. Click **Sync** on `vncmail-prod` in the ArgoCD UI. This stays a
|
||
permanent manual gate — there is no plan to automate this step, ever.
|
||
6. Smoke test against the real hostname, watch Phase 5's dashboards, then
|
||
proceed with Phase 7's staged ramp.
|
||
|
||
Nothing in Phases 1–8 requires the go-live sequence to happen first — build
|
||
and verify the scaling story in isolation (e.g. on `dev-k8s` at smaller
|
||